Mr Openreach man came. Tests showed HR fault and failed between the UG DP and BT66.
Testing from the UG junction box showed HR on 4 out of the 5 pairs. Guy phoned up to request a new lead in but this was declined by his boss because there was still one spare pair, which is what Im now on. Full DLM reset done. This line doesnt sync quite as high as the old one, but whilst he was here it wasnt throwing any errors so its classed as ok.
He said he wouldnt be too surprised if that failed at some point either as that only just was classed as within acceptable params, but nothing more he could do without Openreach installing a new lead in which would mean digging up parts of the pavement and my drive.
Some bizarre behaviour here, or things don't add up right ??
Talking in general terms, as I'm obviously not on site ...... if you have a BT66 there's a fair-to-middling chance your property is fed via duct from the joint-box outside your premises in the pavement ?? Of course, there's always exceptions to the rule.
To add to the picture, 5pr cables are what were always used 'back then' to feed ducted premise, so my money would be that you do indeed have duct feeding your house.
Our remit has always been that we don't swap pairs in this kind of 'feed cable' as it is easy enough o pull another cable through the duct and re-joint at both ends. Assuming of course the duct hasn't collapsed.
If you had the other kind of 'feed' which was the older armoured cable led directly in the ground (DIG), then a pair change would be acceptable but this would usually be followed up by new duct-work being installed and a new cable being run to your premises.
So, something isn't quite adding up from a remote perspective ?? The only thing I can think of is that you do have the older DIG cable, that has been worked on in the past with newer 5-pair cable jointed to it by way of a repair ?? Thus giving the impression it is the newer ducted installation ??.
Either way, I have never in my entire faulting history had to request the permission of my boss with something as simple as this. The engineer n-site makes this decision as to whether it needs a new length of cable installing, and then will run through with you the best way fro our contractors to attack this. The easiest option is to dig in 'Soft' (Grass/mud), but these guys are very, very good at what they do and any surface dressing will be replaced 'The same as or better' than what is was found in.