Apologies for another question regarding a new FTTC cabinet which has been installed, which will be servicing me.
According to the Openreach site, it is currently on the 'Connect' stage, which it has been for a while now. I noticed someone talking about using the Roadworks.org site to check for any upcoming works from BT and noticed some work is due on 21st - 27th April. I've attached a screenshot from the roadworks site which explains a bit about the work they will be doing - I was hoping that someone could tell me how much work is realistically left. Is it almost ready for me to order Fibre broadband.
Thanks in advance ;D
-
Impossible to answer.
Could still be waiting for fibre, which could require a lot of duct clearing/replacment. Could run into issues connection the power etc etc
-
Thanks for your reply! I did kind of think the information could be a little vague.
I have emailed Openreach in the past, who said they are looking to complete all works by end of April - but this information I pulled from the roadworks site is something relatively new (as in it wasn't mentioned on their site when I was speaking with Openreach) - So kinda still hoping completion is scheduled by end of the month.
-
Not impossible.
If the fibre and tie pairs are already connected, it could be very quickly after power is connected if there's a commisioning engineer available to do the required testing.